GRAPHIC TAKE-OFF METHOD (II)
***VER "WATER JET CUTTING BLOG"
$139,500.00
New - 2012
SPECIFICATIONS:
X-Axis travel............................................................120"
Y-Axis travel.............................................................60"
Z-Axis travel............................................................4.5"
Pump output........................................................66,000 PSI
Table length.............................................................168"
Table width...............................................................90"
Dimensions - approximate (excluding pumps & hopper)..........14' x 8' x 7'(H)
Weight - approximate (without water)...............................5,000 Lbs.
Weight - approximate (with water).................................15,000 Lbs.
EQUIPPED WITH:
AT2010 CNC controller
Softec Waterjet Cutter software
ESP 66 Pump
PAC 60 5-axis cutter head
Adjustable water height control for submerged cutting
60-degree beveling capacity
0.9 INCHES/MINUTE *Preliminary specifications subject to verification
CALCULO DE LA HORA PRODUCCION
NOMBRE DE EL EQUIPO:
TECHNI WATERJET
DATOS:
PRECIO ORIGINAL $139,500.00
VIDA EN HORAS 12000
VALOR DE DE RESCATE $20,925.00
CUTTING VELOCITY 0.1 TO 3000 "/MIN
CARGO FORMULA
CALCULO COSTO POR HORA
DE LA MAQUINA
DEPRECIACION = (Va-Vr/Ve (139500-20925)/12000 = 9.88 $/HR
Va=$ 139,500.00
Va=VALOR DE ADQUISICION
Vr= $ 20,925.00 Vr=VALOR DE RESCATE DE LA MAQUINA 5%
Ve=12000 Ve=VIDA ECONOMICA EN HORAS
INVERSION =(Va+Vr)i/2Ha 13.37 =13.37 $/HR
i=TASA DE EINTERES
i=9%
Ha=HORAS DE VIDA DE LA MAQUINA EN UN ANO (1200 HRS/WEEK)
Ha=1250
SEGUROS =(Va+Vr)S/2Ha 256.68 =0.02 $/HR
S=PRIMA DE SEGUROS
ALMACENAJE =KaD= 0.20 $/HR
D=DEPRECIACION POR HORA EFECTIVA DE TRABAJO
D=.02
Ka= COEFICIENTE EXPERIMENTAL O CALCULADO
MANTENIMIENTO =QD = 0.79 $/HR
Q=.08
Q=COEFICIENTA EXPERIMENTAL
COMBUSTIBLES =cPc ELECTRICIDAD 220VOLTS 6.00
c=CANTIDAD NECESARIA DE COMBUSTIBLE POR HORA EFECTIVA DE TRABAJO= 0.6 $/KW-HR
Pc= PRECIO UNITARIO DE EL COMBUSTIBLE
LUBRICANTES =aPl
a=CANTIDAD DE ARENA USADA PARA CORTAR POR HORA EFECTIVA DE TRABAJO
ABRASIVE GARNETT
LLANTAS =VII/Hv ************************************************(NO APLICA)
OPERACION =Sa/H
Sa=SALARIO POR TURNO DE EL PERSONAL
H= HORAS TRABAJADAS POR LA MAQUINA =37.4 $/HR
TOTAL COST 44.41 $/HR